Utah Department of Transportation press release.
US Highway 6 reconstruction and widening from milepost 201 to 203 (Skyview to Tucker).
Description of work and Completion Dates:
North shoulder widening – April 24 to May 10.
Clearing on both shoulders – April 28 to May 1.
Work locations:
North shoulder, milepost 201 to 202.2 (near Tie Fork rest area).
Lane restrictions and directions:
One-way traffic, Monday thru Thursday, 9 p.m. to 5:30 a.m.
Traffic management plans or detours:
Flagging operation for one-way traffic, Monday thru Thursday, 9 p.m. to 5:30 a.m.
Work times and days of the week:
Day: Monday thru Saturday, 7 a.m. to 5:30 p.m.
Night: Monday thru Friday, 6:30 p.m. to 5:30 a.m.
Impacts to access:
Rest area closed from April 23 to May 7 for water pump repairs, unrelated to project construction.
Schedule for coming week:
North shoulder widening and clearing on both shoulders continues. Drilling at Soldier Creek structure.