Construction in Nine Mile Canyon to Continue Until September

2014-NMC-Rd-Paving-Proj-Map.jpg

Starting May 19, Nielson Construction will start doing culvert repair work as well as new culvert installations in various areas in the Nine Mile Canyon. This culvert work will require flagging operations during daytime hours, Monday-Friday. Expect 10 -20 minute delays. This work will be ongoing for the next 3 – 4 weeks.

Paving is scheduled to begin in the middle of June in Soldier Creek Canyon and progress towards the North East. As the paving operation begins, there will be crews ahead of the paver prepping the roadway. During paving, there will be flagger operations controlling traffic. Expect 10-20 minute delays each direction during daylight hours, Monday-Friday. Paving will be on going throughout the summer and into September.