Southeastern Utah Weekly UDOT Construction Report

377829b055e89e3afb894e7528a10996.jpg

The following are descriptions of the construction projects going on in the area:

Emery County

S.R. 10, Cottonwood Wash Bridge

Contract: Gerber Construction (2 locations)
Amount: $711,716
Location: Castle Dale
Impact: * Stoplight with alternating one-way traffic * Traffic may shift to the other lane this week
Activity: * Bridge deck repairs * Paving

В 

S.R. 19, Green River Main Street
Contract: Nielson Construction
Amount: $2,366,972
Location: Green River Business Loop
Impact: * Minor delays
Activity: * Painting * Raising manholes * Asphalt repair

U.S. 6, Milepost 272 To Woodside
Contract: Nielson Construction
Amount: $3,869,924
Location: 22 Miles north of Green River
Impact: * Narrow lanes, one in each direction
Activity: * Sub-grade work

Grand County

I-70, Yellowcat to West Cisco
Contract: Geneva Rock
Amount: $2,255,629
Location: East of Thompson Springs Welcome Center
Impact: * Single lane closures in both directions
Activity: * Rotomilling * Paving

San Juan County

U.S. 191, Crack Repairs
Contract: Frehner Construction
Amount: $3,029,434
Location: South of Bluff, Mileposts 12 to 21
Impact: * Potential delays of up to 15 minutes during the daytime
Activity: * Workers are finishing road surface and installing barriers

U.S. 191, Blanding Main Street
Contract: LeGrand Johnson Construction
Amount: $1,730,539
Location: Blanding Cemetary on Grayson Parkway to 2000 South Main
Impact: * Occasional one-way traffic
Activity: * Finish paint striping * Project clean-up