Road construction continues on State Road 10 and Huntington Main Street, as well as on two projects on I-70 this week. The following is a summary of those Utah Department of Transportation projects:

Carbon County

S.R.10, South Price to Stake Farm Road
Contract: Nielson Construction
Amount: $1,840,710
Location: South of Price
Impact: Single lane traffic during evening hours
Activity: * Paving beginning south of River Road and working north * Backfilling near culverts

Emery County

S.R. 10, Huntington Main Street
Contract: Geneva Rock Products
Amount: $745,506
Location: Huntington Main Street
Impact: Access modifications
Activity: * Construction of pedestrian sidewalk ramps on corners * Milling road surface * Soft spot repairs

Grand County

I-70, Yellowcat to West Cisco
Contract: Geneva Rock
Amount: $2,255,629
Location: East of Thompson Springs Welcome Center
Impact: Single lane closures
Activity: Grinding rumblestrips

Sevier County

I-70, Wide Hollow To Fremont Junction
Contract: Nielson Construction
Amount: $4,534,747
Location: Salina Canyon, Mileposts 83 to 89
Impact: * Single lane closure in each direction * No delays expected
Activity: * Paving * Guardrail installation