Two Waste and Water Improvement projects that started months ago are nearing completion, according to Price City Engineer Russell Seeley.

One of the two projects, stretching from 300 to 600 East on 400 North, included a sewer line replacement as well as the replacing of a storm drain. Both replacements have been completed and the reconstruction of the road is currently in processes. Paving will hopefully begin within the coming weeks so that the road may be accessible before school starts at the end of August.

The second of the two projects, found on 400 South from 400 to 700 East, was a water main replacement. The replacement has also been finished and the road, similar to the work found on 400 north, is in the process of being reconstructed. Though not as pressing with no educational facility nearby, the road will hopefully be paved within the next few weeks as well.