Highway 6 Construction Update

UDOT.png

Utah Department of Transportation press release. 

US Highway 6 reconstruction and widening from milepost 201 to 203 (Skyview to Tucker).

Description of work and Completion Dates:

North shoulder widening – April 24 to May 10.

Clearing on both shoulders – April 28 to May 1.

Work locations:

North shoulder, milepost 201 to 202.2 (near Tie Fork rest area).

Lane restrictions and directions:

One-way traffic, Monday thru Thursday, 9 p.m. to 5:30 a.m.

Traffic management plans or detours:

Flagging operation for one-way traffic, Monday thru Thursday, 9 p.m. to 5:30 a.m.

Work times and days of the week:

Day: Monday thru Saturday, 7 a.m. to 5:30 p.m.

Night: Monday thru Friday, 6:30 p.m. to 5:30 a.m.

Impacts to access:

Rest area closed from April 23 to May 7 for water pump repairs, unrelated to project construction.

Schedule for coming week:

North shoulder widening and clearing on both shoulders continues. Drilling at Soldier Creek structure.