Southeastern Utah Weekly UDOT Construction Update

af06806ddd1231b8086cf9d0c7570813.jpg

The following is a summary of the projects that are continuing in Southeastern Utah:

Carbon County

S.R. 10, South Price to Stake Farm Road

Contract: Nielson Construction

Amount: $1,840,710

Location: South of Price

Impact: Minimal traffic interruption.

Activity: Seeding & painting.

Emery County

I-70, West of Green River

Contract: Staker Paving & Construction

Amount: $5,243,024

Location: Mileposts 138 to 141 and 153 to 155

Impact: One lane closed in each direction.

Activity: Rotomilling between mileposts 138 and 141.

U.S. 6, Section Resurfacing

Contract: Nielson Construction

Amount: $1,070,254

Location: Mileposts 262 to 263, Mileposts 270 to 272 & Mileposts 273 to 276

Impact: Work may occur anytime day or night Monday-Thursday; Single lane traffic with pilot operations; Delays of up to 15 minutes.

Activity: Rotomilling and paving around the clock beginning at the north end of the project and working toward the south.

Grand County

U.S. 191, Moab to State Route 279

Contract: W.W. Clyde & Co.

Amount: $6,451,900

Location: Between 400 North and Potash Road, Moab

Impact: Minimal traffic impact expected.

Activity: Traffic barrels may go up by the end of the week; Contractor anticipates beginning roadwork September 26th.